132kV Gridyard Upgrade

Taking a lead commissioning role in substation projects is always a rewarding experience, requiring a proactive whole-system approach and collaboration with a number of different interested parties. Our engineer helped to deliver a major expansion project at Urenco UK, which is a nuclear enrichment facility in Cheshire important to the UK’s nuclear power industry. The project included a new 132kV mesh corner, one Gridyard transformer and two brand new 11kV substations.

Project Description

We were pleased to be involved in the intake substation upgrade project at Urenco UK.  The existing electricity supply to the facility comprised of three 132kV feeders to separate 132kV/11kV transformers, which all supplied one 11kV substation.  To boost incoming supply capacity, two brand new switchboards were installed to replace the existing intake substation.  One additional 132kV feeder was also constructed in the form of a new mesh corner and one new Gridyard transformer was installed.

There were design complexities at all levels of the project, and several parties involved including the client, the principal contractor, the transmission network operator National Grid and the distribution network operator Scottish Power.

We assisted the principal contractor with commissioning of the new mesh corner and Gridyard transformer.  This included full secondary injection tests of the new protection and control panels, Site Acceptance Tests of some primary equipment such as the 132kV current transformers, and primary injection tests of the 132kV protection system.  Our engineer also designed and implemented the Delayed Auto Reclose system logic used in the new control panels.

Later in the project, we were involved in the commissioning of the 11kV substations.  Our scope included commissioning of the 11kV protection relays and end-to-end testing of the pilot differential protection.  We also completed Site Acceptance Tests on the 11kV distribution transformers and reactors.  Our engineer helped to redesign the bespoke 11kV interlocking system between the 11kV and 132kV systems.

Project Gallery

Related Post

Offshore Commissioning

Culzean is a UK offshore facility located in the North Sea, 140 miles off the coast of Aberdeen. The gas condensate field can meet up to 5% of the United Kingdom’s gas demand. Our engineers commissioned three Siemens STG300 Gas Turbine Generators on the Culzean Platform. Commissioning services for the three GTGs included both onshore static testing of the generators and the subsequent offshore dynamic commissioning.

Read More »

Survey and Retrofitting

At Gradient Power Ltd. we come across many interesting projects requiring bespoke design and implementation. The Generator Control Panels upgrade at Boots Plc. in Nottingham was one such project. Our engineers conducted a site survey, recommissioned the control panels with modern upgrades of the excitation and protection systems, completed a new connection agreement with the Distribution Network Operator and carried out power quality measurements to calculate an optimal operating power factor for the generators.

Read More »

Gas Turbine Generator Commissioning

Sagar Samrat is an offshore oil rig owned by the Oil and Natural Gas Corporation, ONGC. It was India’s first oil drilling rig, built in 1973. The platform was recommissioned in 2019 at GPC shipyard in Abu Dhabi, UAE before sailing away to the west coast of India, 145km off the coast of Mumbai. It is an ultra-deepwater rig capable of drilling at depths of up to 12km. Our engineer commissioned the two Siemens SGT300 Gas Turbine Generators which provide power to the rig, whilst onshore in Abu Dhabi.

Read More »