Our scope was to complete Site Acceptance Testing and commissioning of two 33kV circuit breakers and four 11kV switchboards. We conducted a complete inspection of the newly installed switchgear against approved drawings, manufacturer’s requirements and applicable standards. This included switchgear alignment, busbar connections, clearances and cable terminations.
The scope also involved primary testing to prove insulation integrity and joint continuity, as well as secondary injection testing to prove all protection relays, metering and controls associated with the switchgear. Each protection function was verified under simulated fault conditions. We supervised the initial energization to confirm correct operation and monitor temperature rise and load sharing between bus sections. The interface between the switchgear control systems and the building SCADA system was also verified during the commissioning.
This was an incredibly rewarding project for our engineers and we were pleased to play a critical part in the construction of this impressive building.