Survey and Retrofitting

At Gradient Power Ltd. we come across many interesting projects requiring bespoke design and implementation. The Generator Control Panels upgrade at Boots Plc. in Nottingham was one such project. Our engineers conducted a site survey, recommissioned the control panels with modern upgrades of the excitation and protection systems, completed a new connection agreement with the Distribution Network Operator and carried out power quality measurements to calculate an optimal operating power factor for the generators.

Project Description

Our commissioning engineer carried out a site survey at the Boots factory in Nottingham to assess the condition of the existing Generator Control Panels, GCPs, for the three Gas Turbine Generators on site.  We detailed the components inside the panels and provided recommendations for repair, testing or upgrade.  The client acknowledged the excitation and protection systems were obsolete and a modern upgrade of the system was carried out.

The legacy C10/120 excitation systems were upgraded to a Basler DECS250 AVR and the Alstom MiDOS protection relays were replaced with the Siemens Siprotec 7UM62. The scope of work included recommissioning the retrofitted GCPs, static checks on the generators, a new interface wiring design, secondary injection tests of the new protection relays, and dynamic commissioning of the excitation and synchronising systems.

Our engineers also dealt with the connection agreement between the client and the network operator National Grid Electricity Distribution. The Boots site has two grid network incomers, of which only one incomer had an existing contract. Our engineers successfully arranged a new connection agreement between the site and National Grid.  We also attended site to test the updated G59 protection as part of the new agreement.

Finally, we were asked to determine an optimal Power Factor for the three generators, considering the fluctuating factory load and the cost-benefit of exporting and importing real and reactive power from the grid.  We installed power loggers in the GCPs to collect data.  We then analysed the data to deduce the site reactive power requirements and determine the most economical operating Power Factor for the three generators.

Project Gallery

Related Post

Offshore Commissioning

Culzean is a UK offshore facility located in the North Sea, 140 miles off the coast of Aberdeen. The gas condensate field can meet up to 5% of the United Kingdom’s gas demand. Our engineers commissioned three Siemens STG300 Gas Turbine Generators on the Culzean Platform. Commissioning services for the three GTGs included both onshore static testing of the generators and the subsequent offshore dynamic commissioning.

Read More »

132kV Gridyard Upgrade

Taking a lead commissioning role in substation projects is always a rewarding experience, requiring a proactive whole-system approach and collaboration with a number of different interested parties. Our engineer helped to deliver a major expansion project at Urenco UK, which is a nuclear enrichment facility in Cheshire important to the UK’s nuclear power industry. The project included a new 132kV mesh corner, one Gridyard transformer and two brand new 11kV substations.

Read More »

Gas Turbine Generator Commissioning

Sagar Samrat is an offshore oil rig owned by the Oil and Natural Gas Corporation, ONGC. It was India’s first oil drilling rig, built in 1973. The platform was recommissioned in 2019 at GPC shipyard in Abu Dhabi, UAE before sailing away to the west coast of India, 145km off the coast of Mumbai. It is an ultra-deepwater rig capable of drilling at depths of up to 12km. Our engineer commissioned the two Siemens SGT300 Gas Turbine Generators which provide power to the rig, whilst onshore in Abu Dhabi.

Read More »