The scope of work for the two GTGs involved static checks on the generators and the current and voltage transformers, as well as commissioning tests on the Generator Control Panels. Commissioning the control panels included setup and secondary injection tests of the Beckwith protection relays, the Woodward synchronising controllers, the metering units and the Basler DECS200 excitation systems.
The generators were dynamically tested using on-site load banks. The Basler excitation systems and the synchronising systems for the generator circuit breakers were fully commissioned. Dynamic testing also included load accept and reject tests, voltage regulation checks, load sharing setup and excitation limits checks. This ensured reliable generator operation for the drilling rig load. The control system was tuned to optimize resilience and performance.
With our extensive expertise in power systems and electrical testing, our engineers delivered fully commissioned generators ready to provide a resilient power supply for the drilling rig.